About projects

Nobelwind

DESCRIPTION NOBELWIND NV
- A special purpose vehicle, totally separate from Belwind NV
- Created in order to isolate the development risk of Belwind 2
- Has as sole purpose the development, financing, construction and operation of the Nobelwindwind farm
- Is directly and indirectly owned by experienced and committed shareholders with strong track records and solid financial capacity

http://www.nobelwind.eu


PRELIMINARY PLANNING

- Information package: July 2015
- Financial Close: October 2015
- Start of Construction: April 2016
- Project Completion: December 2017

DETAILS

- Location: Belwind concession (North Sea)
- Distance to shore: 47 km
- Area: 19.8 km2
- Relevant sea depth: 26 to 38 meters (avg. 33 meters)
- Average wind speed: 9.3 m/s (90m LAT)
- Expected Capacity: 165 MW
- Expected Construction start: Spring 2016
- Export Cable (already installed):
- 220kV interconnector cable to the Northwind OHVS
- Sharing of 220kV Northwind export cable
- Expected Annual Production: 679 GWh

Main permits:
- In place
- Concession split and partial transfer to Nobelwind

Northwind

The Northwind wind farm is located on the Lodewijkbank, 37 km off the Belgian coast.
Phase 1 of the project, in operation as of May 2014, comprised the construction of 72 wind turbines, generating 3 MW each.

The farm provides green energy for 250.000 Belgian households.

http://northwindenergy.eu



Facts & figures Northwind Phase I

• 72 Vestas V112 turbines
• location: Lodewijkbank, 37 km off shore
• area: 14,5 km2
• diameter rotor: 112 m
• power per turbine: 3 MW
• total power: 216 MW
• green electricity for 250.000 Belgian households
• annual saved CO2 emissions: 255.000 tonnes
• operational since May 2014

Belwind

The Belwind wind farm is located on the Bligh Bank, 46 km off the Belgian coast.

Phase 1 of the project, in operation as of December 2010, comprised the construction of 55 wind turbines, generating 3 MW each.
The farm provides green energy for 160.000 Belgian households.

http://www.belwind.eu


Facts & figures Belwind Phase I

• 55 Vestas V90 turbines
• location: Blight Bank, 46 km off shore
• area: 17 km2
• height above sea level: 117 m
• total construction height: 189 m
• diameter rotor: 90 m
• power per turbine: 3MW
• total power: 165 MW
• green electricity for 160.000 Belgian households
• annual saved CO2 emissions: 270.000 tonnes
• operational since December 2010